This guide from Korea Midland Power sets out the permits needed to build and run a power plant in Korea, from site selection to commercial operation. It covers the generation business licence, approval of the construction plan, land development permits, environmental and disaster impact reviews, grid connection with KEPCO, pre-use inspection and confirmation of renewable facilities for certificates. Foreign investors in solar, wind, fuel cell or energy storage projects can use it to plan the sequence of approvals, the authority that grants each one and the main size thresholds.

Electric Utility Act전기사업법Korea Midland Power Co. (KOMIPO)

Key points

  • Generation business licence (Electric Utility Act Art. 7) Plants above 3,000 kW apply to the Ministry of Trade, Industry and Energy (Electricity Commission). Plants of 3,000 kW or less apply to the provincial governor. In Jeju, wind farms up to 20,000 kW apply to the Jeju governor, and larger wind farms require consultation with the Ministry.
  • Construction plan for generating facilities Installing a plant of 10,000 kW or more needs approval from the Ministry of Trade, Industry and Energy. Installing a plant below 10,000 kW only needs a report to the provincial governor. The same split applies to solar, fuel cell and energy storage equipment, with 10,000 kWh as the threshold for battery capacity.

Read the full explanation

  • 6 more points with the exact figures and conditions.
  • Who it affects and what to do about it.
  • Ask IndoyangAI how it applies to your company.

Source

More rules

Source: a document published by a Korean government agency on data.go.kr, under the Korea Open Government License (공공누리). Explained by Indoyang Connect with AI assistance. This is not legal advice: the document may have been updated since, so check the current law before acting.